Case & Project History

Location: EUROPE
YEAR PROJECT OWNER PIPES DOWNLOAD
2021 Onshore projects Snam Rete Gas 60 Km different diameters and thickness
2021 Offshore projects Tenaris (c/o Geocean) 3 Km 400mm x 12,7mm
2021 Baltic Pipe Onshore Project GAZ System 40'' OD x14,2mm WT quantity 11.700 meters / 40'' OD x 22,2mm WT quantity 700meters
2021 Israel Natural Gas Line INGL Israel Natural Gas Lines Ltd
2020 Interconnector Greece-Bulgaria project onshore ICGB 32''
2020 Baltic Polen Offshore Project GAZ System
2020 Onshore projects Snam Rete Gas different diameters and thickness
2020 Onshore projects Vallurec ( c/o Sonatrach) 50 Km 150mm x different thicknesses
2020 Iskenderun TDC Liman Projesi Tosyali Demir Celik 1,1 Km 406,4 x 8 mm - 1,1 Km 508 x 8 mm - 610 x 8mm
2020 Aliaga- Kinik Dogalgaz Boru Hatti Botas 13,197 Km 508 x 6,4 mm
2020 Aliaga- Kinik Dogalgaz Boru Hatti Botas 2,114 Km 508 x 7,14 mm
2020 Nurdagi Dogalgaz Deplasesi Projesi Firat Insaat 1016 x 12,1 mm / 1168 x 12,1 mm
2020 Denizli Icme Suyu Ishale Hatti DSI 8,2 Km 1118 x 8,8 mm
2020 Gaziantep Icme Suyu Ishale Etti DSI 5,2 Km 1219 x 10 mm
2020 Tuz Golu Dogalgaz Depolama Projesi China Camc Engineering Co.Ltd .Ic 73 Km 1321 x 11,13 mm / 1321 x 12,70 mm / 1524 x 12,7 mm / 1524 x 14 mm
2020 Terkos Ikitelli Isale hatti ISKI 2 Km 2540 x 21 mm
2019 Polish Gas Pipeline System expansion by Gaz System S.A. Gaz System S.A. 40” - ca. 38 000 km in various parts, “Pogórska Wola – Tworzeń pipeline”, “Strachocina – Poland/Slovakia border pipeline”
2019 Zeelink
2019 Pijp G300
2019 CAPACITY4GAS NET4GAS s.r.o. 96 Km
2019 EBK NET4GAS s.r.o.
2019 Flughafen Muenchen
2019 Water Pipe 200 Km
2019 Gaziantep Icme Suyu Ishale Etti DSI 20 Km 1219 x 10 mm / 2438 x 22 mm
2019 Brau Dogalgaz Boru Hatti Romanya 133,5 Km 813 x 10 mm / 813 x 11 mm / 813 x 14,2
2019 Terkos Ikitelli Isale Hatti ISKI 13 Km 2540 x 21 mm
2019 Turk Akimi Dogalgaz Boru Hatti Botas 35,5 Km 1219 x 14,2 mm /1219 x 20 mm
2019 Afyon - Seckoy Dogalgaz Boru Hatti Botas 42 Km 1016 x 11,9 mm
2018 - 2019 Ballough Bypass 1 Km
2018 - 2019 Tsechechische Republik NET4GAS s.r.o.
2017 - 2019 Eugal Gascade Gastransport 486 km
2017 - 2019 Nordstream 2 Nord Stream AG 200 Km
2018 Turkish Stream Botas 22 Km 48''
2018 Eustream Slovakia 75 Km 40''
2018 Terminal Piling Pipes Botas 7 Km 900-1200-1400 mm
2018 Middle East Piling Project 21 Km 16-20-24''
2018 Terkos Water Pipeline Project Iski 3,5 Km 100''
2018 Middle East Water Pipeline Project 43 Km of several diameters
2018 Gaziantep Drinkable Water Pipeline 33,5 Km 2642-2438-1219 mm
2018 Elazig Drinkable Water Pipeline 20 Km 1524 mm
2018 Trabzon Drinkable Water Pipeline 23 Km 711-813-914-1016-1118-1626-1727 mm
2018 Brau natural Gas Pipeline 79 Km 813 mm
2018 Botas Aliaga DGBH Botas 22 Km 914 mm
2018 Stationsrohre Eugal Gascade Gastransport 4 km
2018 Etzel-Suedfeldleitung
2018 Stationsrohre Radeland 1,5 km
2018 Stationsrohre Lubmin 1,1 Km
2018 Goleniow-Ploty - GAZ System GAZ System 5,8 Km
2018 Open Grid
2018 Flaboform
2018 Stahlrohr
2018 Not given Not given 0,6 Km - 457mm
2017 Drinking Water Project - Trabzon Kalyon/DSI 47,7 Km 711-2032 x 7,1-17,5 mm - Steel grade S275JR
2017 Goksu Basin Based Water Supply Project - Gaziantep Kaylon/DSI 120 Km 1422-2642 x 10-25,4 mm - Steel grade S275JR
2016 - 2017 Nurdagi Crude Oil Pipeline - Gaziantep Botas 24,5 Km 457-1168 x 7,1-11,9 mm - Steel grade X65M
2016 - 2017 Nord Stream II-III° Pipeline Nord Stream AG Consortium Germany Russia 48" x 26,8-34,9- 41 mm - Steel grade X70
2016 - 2017 Not given Mavi Tünel 10 Km 610mm -1829mm -1016mm
2016 - 2017 Düzce Project Botas 65 Km 508mm
2016 - 2017 Sirnak Project Botas 55 Km 323 mm
2016 - 2017 Water Pipeline Project Iski 33 Km 1016mm -914mm -813mm -1219mm
2016 - 2017 Not given Israil Gas 21 Km 914 mm
2016 - 2017 Lübnan Project Not given 5 Km 1730 mm
2016 - 2017 Hakkari Project Botas 3 Km 1016 mm
2016 Ivedik Project - Ankara Ulubol/Aski 6,4 Km 2,235 X18 mm - Steel Grade S275JR
2016 Izmir Lng Terminal Project - Izmir Kalyon - Kolin 9 Km 914 X14,3 mm - Steel Grade X65
2015-2016 Melen Project - Istanbul Iski 37,5 Km 3,048 X25 mm - Steel Grade S275JR
2015-2016 Istanbul 3rd Airport Waterline - Istanbul Iga 12 Km 2,235 X17,5 mm - Steel Grade S275JR
2014-2015 South Stream - 1st Pipeline South Stream Transport B.V. 1st pipeline string with pipe diam. 813 mm x 39 mm (total km 931)
2014-2015 Izmit Yarimca Container Port Project - Izmit Yarimca Stfa Holding 34 Km 1,219 X19-23 mm - Steel Grade S355JR
2013-2014 Diyarbakir Waterline Project Diyarbakir Hmc/Dsi 26 Km 711-813 X7,1-14 mm - Steel Grade S275JR
2013-2014 Cokal Waterline Project - Tekirdag Cokal Kamer Insaat /Dsi 27 Km 610-914 X5-8,7 mm - Steel Grade S275JR
2012-2013 Van Waterline Project - Van Oz Aras Grup - Abdurrahim Temiz /Dsi 33 Km 2,032 X17,5 mm - Steel Grade S275JR
2012-2013 Yazici Port Piling Project - Iskenderun Diler Holding A.S. 29 Km 1,118 X14 mm - Steel Grade S355JR
2012-2013 Water Pipeline Pedro Arco Pedro Arco - Spain 610 mm x 5 mm - 0,730 km / 711 mm x 5,6 mm - 3,22 km / 914 mm x 6,4 mm - 4,850 km / 813 mm x 6,4 - 1,165 km
2012-2013 Water Pipeline Isdemir Isdemir - Turkey 1.829 mm x 16 mm - 8,171 km / 1.219 mm x 16 - 0,200 km
2012-2013 Water Pipeline Montornes La Roca Montornes La Roca - Spain 813 mm x 7,1 mm - 2,536 km
2012-2013 Water Pipeline Torrevieja Torrevieja - Spain 1.219 mm x 7,1 mm - 2,926 km / 1.320 mm x 7,9 mm x 5,244 km
2012-2013 Transgaz Natural Gas Line Transgaz - Romania 700/800 mm x 40 km
2012-2013 Water Transmission Project - Italy not given 1.200 mm x 23,5 km
2012-2013 Natural Gas Line Botas Diyarbakir Pipeline Project Botas Diyarbakir - Turkey 400/1.000 mm x 43 km
2012-2013 Water Pipeline - Spain Potable Water Project Spain Potable Water 219/813 mm x 76,133 km
2012-2013 Angodos Rio Verde Water Pipeline Angodos - Spain not given
2012-2013 Natural Gas Line - Botas Kilis Project Botas - Turkey not given
2012-2013 Water Pipeline Torrevieja Torrevieja - Spain 1.620 mm x 9,5 mm - 5,680 km 1.420 mm x 8,7 mm - 7,724 km
2009-2010-2011-2012 Nord Stream I - Nord Stream II Nord Stream AG Consortium - Germany/Russia various diameters (not given details)
2012 Water Pipeline Tubi Spa 4 Km 3048x25 mm - STEEL GRADE S275JR
2011-2012 Ivedik Project - Ankara Ulubol / Aski 8,2 Km 2235-2540 X18 mm - Steel Grade S275JR
2011-2012 Ivedik Project - Ankara Ulubol / Aski 8,2 Km 2235-2540 X18 mm - Steel Grade S275JR
2011-2012 Aydin Waterline Project - Aydin Abdurrahim Temiz Insaat / Dsi 5 Km 1,219 X10 mm - Steel Grade S275JR
2011 Yumurtalik Port Project - Adana Sanko Holding 8 Km 1,118 X16 Mm - Steel Grade S355JR
2010 Nel Pipeline - 1st section Greifswald to Lueneburg 2nd section - Luneburg district to Rehden E.ON Ruhrgas (Germany) - Wingas (Germany) 48" x 1st section 241 km - 48" x 2nd section 194 km
2010 Water Pipeline Tubi Spa 9 Km 1829x14,5 mm - STEEL GRADE S355JR
2010 Water Pipeline Tubi Spa 28 Km 711-1321 X14,5-11 mm - Steel Grade S355JR
2009-2010 Opal Pipeline - Nord Stream - Ostsee Pipeline Anbindungs-Leitung E.ON Ruhrgas (Germany) - Wingas (Germany) 56" X 480 km
2009-2010 Water Pipeline Welm Add Welm Add - UK not given
2007 Steel pipe for high pressure pipelines to Ambelia-Karditsa-Trikala Public Gas Corporation of Greece 10" - 72 km
2007 Steel pipe for medium pressure pipelines various areas of Greece Public Gas Corporation of Greece 10" - 8" - 6" - 4" 46 km
2007 Potable water pipeline Michaniki SA 40" - 44" - 48" 12 km
2006-2007-2008 - SNAM 34" - 48"
2006-2007 Steel pipe for potable water pipeline Tholos SA 2006: 24" - 34 km; 2007: 28" - 32"
2006 Steel pipe for irrigation system Ergas SA 2006: 28" - 15 km; 2007: 32" -36" -40" -44"
2006 Katarina Marica Inagip Croazia 14" - 17 km
2006 - Edison 36"
2006 Steel pipe for medium pressure pipelines - Various areas of Greece Public Gas Corporation of Greece 10" - 8" - 6" - 4" 72 km
2006 Workum-Wieringermeer Nederlands Gasunie n.v. 48" - 4,4 km
2006 Ruhrgas Egl Lauterbach Scheidt und Tothenstadt-Schwandorf 40" - 98 km
2005 Snam Rete Gas Snam Rete Gas Italia 56" 30 Km
2004 Snam Rete Gas Snam Rete Gas Italia 48" 33 Km
2004 Turkish Gas Project Turkey
2003 Agip - Thea Amelia Eni - Divisione Agip 10" 33 km
2003 Multicore Rotterdam Havenbedrjf Rotterdam 6" 19 km 4" 19 km
2002 Pra Oil Pra Oil 30" x 12,7 mm 1,5 km
2002 Trans Gas Portugal Sines - Setubal - Palmela Trans Gas Portugal - Gas 28" - 32" 89,5 km
2002 Rete Gas Italia SNAM ENI Group Rete Gas Italia SNAM 12" RIV1 56" RIV3 30"- 48" RIV5 ca 60 km
2002 Q1 - QB Development project north sea off-shore CLYDE PETROLEUM 10" - 12" - 20" - 36" 1,5 + 1,6 + 1,8 + 0,13 km
2001 Gas Project Camuzzi 8" - 16" 79 km
2000-2001 Enagas Enagas - Gas 4" - 12" 630 km
2000 British Steel - Gas Project British Gas 8" - 20"
1999-2000 Agip - ENI Group Agip - Gas 6" - 16" 229 km
1998 Dogubeyazit Erzorum Natural Gas Pipeline Fernas Stfa Enerkom - Gas 40" 97 km
1998 Distrigaz Distrigaz - Gas 6" - 12" 32 km
1997-2001 Depa Depa - Gas 6" - 18" 250 km
1996-1997 Botas Russian Turkey Gas Pipeline Phase II Botas - Gas 24" - 36" 150 km
1996-1997 Botas Cankanakle Project Botas - Gas 12" 130 km



Immagine Industrie Polieco